Stone34 is going up fast. They sent this about construction updates: Watch the progress at our live webcam!

  • The tower crane [was] be delivered to the site… Saturday, May 11th. North 35th St. [was] closed from Stone Way to just past the transfer station entry from 9am until 6pm and crews will be at work.
  • Shotcrete (concrete applied by hose onto vertical surfaces) will be applied to the shoring walls beginning on May 13.
  • Over seven tons of material was diverted from the landfill during March. Stone34’s overall recycling rate to date is 97%!

Project Manager Tony Hill is the site contact and can be reached at 206-726-8000. ”